· By Mark Tindall
Water damage repair in a daylight-basement bathroom, Wedgwood

The short version
The owners of this Wedgwood house, built around 1950, had water damage in their daylight basement, followed by a SERVPRO mitigation, leaving extensive damage to the drywall and moldings. I reframed where needed, installed new drywall and new molding, and repainted. The job took 16 days.
Project facts
The problem
This Wedgwood house was built around 1950, and its daylight basement had taken on water, in an area that includes the basement bathroom. The damage was extensive: drywall and moldings throughout the affected area needed to be repaired or replaced. Some of that damage came from the water itself, and some from the SERVPRO mitigation crew that dried the space out afterward.
How I did it
Open it up and rebuild the framing. With the damaged drywall cut away, I reframed where the structure behind it needed it, so the new walls and ceiling had something sound to attach to.
New drywall. I installed new drywall over the rebuilt framing.
New molding. The damaged moldings were replaced with new molding.
Repaint. I repainted the repaired areas to finish the job.
Why this approach
Water damage usually happens in two rounds. The first is the water. The second is the mitigation: a crew like SERVPRO comes in to dry the space fast and stop mold before it starts, and that work is deliberately destructive. Wet drywall gets cut out, often in a straight line partway up the wall or across the ceiling, baseboard and trim come off, and soffits and walls get opened so air can reach the framing. That's the right call for the house, but it leaves a space that's open, mismatched and unfinished.
So this job had to put back both: what the water ruined and what the drying-out removed. Reframing first made sure the new drywall had sound, straight backing. New drywall and new molding throughout, rather than patching around the cuts, mean the repairs don't show, and the repaint ties the finished room together as if nothing had happened.
Timing
The job took 16 days.